ZEEBRUGGE 13/10/08 - E.T.A RIGA 18/10/08: 798 units of PEUGEOT 308 for the Russian market were discharged from a car-carrier at the Riga Central Terminal (discharging rate: 90 units per hour with one shift).
Project Timeline:
M/V PELANDER:
17/10 AT 01:42 - END OF SEA PASSAGE
03:00 - ARRIVED ON RIGA OUTERROAD
03:24 - PILOT ON BOARD
04:54 - FIRST LINE ASHORE
05:18 - ALL FAST TO BERTH NO. PM-19 (RCT TERMINAL)
05:30 - VESSEL CLEARED IN, FREE PRATIQUE GRANTED
08:00 - DISCHARGING COMMENCED
16:50 - DISCHARGING COMPLETED
17:20 - RAMP SECURED
17:20 - OUTWARD CLEARANCE OBTAINED
17:30 - PILOT ON BOARD
17:45 - VESSEL LEFT BERTH.
ACCORDING TO MASTER VESSEL'S ETA GDYNIA 18-OCT AT 15:00 LT WP.
Shipping line: United European Car Carriers
Port agent: NAVEST SHIPPING / RIX SHIPPING
Forwarder: Gefco Baltic
For more information see corporate website at: http://baltic.gefco.net/gefco-baltic/
_d81a4.jpg)